FIT5057 Week 4: Scope, CPM & NPV Mastery

64 accessible of 64 cards

Card Preview

64 accessible of 64 cards

A quick, read-only look at the deck content.

Term

What is the formal definition of a Work Breakdown Structure (WBS)?

Definition

A hierarchical, product-oriented "family tree" of deliverables that organizes and defines 100% of the project's total scope.

Term

What is the primary purpose of a WBS in scope management?

Definition

To deconstruct complex project goals into manageable, bite-sized deliverable components to maintain baseline control over costs, schedules, and changes.

Term

What does the WBS 100% (Summative) Rule state?

Definition

The work content of any parent element must equal exactly the sum of its subordinate child elements, capturing all planned project work.

Term

What is the scope implication if a deliverable is omitted from the WBS?

Definition

Under the 100% rule, if a piece of work is not captured in the WBS, it is completely out-of-scope and cannot be executed without formal change control.

Term

Why must WBS elements be written strictly as nouns or adjectives?

Definition

Because a WBS is product-oriented, focusing on physical or digital deliverables (nouns) rather than the processes or actions (verbs) used to create them.

Term

What is the grammatical indicator that a branch of the WBS is fully decomposed?

Definition

Decomposition is complete when the planning team naturally begins writing action verbs (activities) instead of nouns (deliverables).

Term

What is a Work Package in the context of a WBS?

Definition

The smallest, lowest-level unit of work in a WBS branch that can be realistically estimated, scheduled, budgeted, and controlled.

Term

What organizational rule ensures accountability for a WBS Work Package?

Definition

The Unity of Responsibility Rule, which states that every individual Work Package must be assigned to exactly one named team member.