Flashcard Deck · 20 cards · Public

PMP Exam Prep - PMBOK 7th Edition Principles, Agile & Hybrid Project Delivery

Master high-yield PMP exam concepts including PMBOK 7th Edition principles, Earned Value Management formulas, Agile ceremonies, and risk strategies for first-time exam success.

Cards in this deck

(20 cards)

Preview terms and definitions before starting your study session.

#1
Term
Cost Performance Index (CPI)
Definition
Formula:
A measure of the cost efficiency of budgeted resources. A value greater than 1.0 indicates performance is under budget, while a value less than 1.0 indicates cost overrun.
#2
Term
Schedule Performance Index (SPI)
Definition
Formula:
A measure of schedule efficiency. A value greater than 1.0 indicates the project is ahead of schedule, while a value less than 1.0 indicates the project is behind schedule.
#3
Term
Cost Variance (CV)
Definition
Formula:
The amount of budget deficit or surplus at a given point in time. A positive value indicates the project is under budget; a negative value indicates over budget.
#4
Term
Schedule Variance (SV)
Definition
Formula:
The amount by which the project is ahead or behind the planned delivery date at a given point. A positive value is ahead of schedule; a negative value is behind schedule.
#5
Term
Estimate at Completion (EAC) - Typical Variances
Definition
Formula:
Used to predict the total cost at completion assuming current cost performance () will continue for the remainder of the project.
#6
Term
PMBOK 7th Ed Principle: Focus on Value
Definition
Continually evaluate and align project outcomes with business objectives, benefits, and value realization rather than focusing solely on deliverables (outputs).
#7
Term
PMBOK 7th Ed Principle: Stewardship
Definition
Be a diligent, respectful, and caring steward. Act with integrity, care, trustworthiness, and compliance while considering financial, social, and environmental impacts.
#8
Term
PMBOK 7th Ed Principle: Tailoring
Definition
Design the project development approach based on context, governance, team, culture, and project characteristics rather than using a rigid, one-size-fits-all process.
Showing 8 of 20 cards in this deck.