Flashcard Deck · 21 cards · Public

PMP - Project Management Professional Certification Prep

Master essential PMP exam concepts, including process groups, predictive and Agile methodologies, core knowledge areas, and critical Earned Value Management formulas.

Cards in this deck

(21 cards)

Preview terms and definitions before starting your study session.

#1
Term
Five PMBOK Process Groups
Definition
The logical grouping of project management processes: 1. Initiating (defining a new project/phase), 2. Planning (establishing scope and objectives), 3. Executing (completing work defined in the plan), 4. Monitoring & Controlling (tracking and regulating progress), and 5. Closing (formally finalizing all activities).
#2
Term
Ten PMBOK Knowledge Areas
Definition
Core operational areas of project management: Integration, Scope, Schedule, Cost, Quality, Resource, Communications, Risk, Procurement, and Stakeholder Management.
#3
Term
Project Charter
Definition
A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
#4
Term
Work Breakdown Structure (WBS)
Definition
A hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. The lowest level is the Work Package.
#5
Term
100% Rule (WBS)
Definition
A core WBS principle stating that the WBS must include 100% of the work defined by the project scope and capture all deliverables (internal, external, and interim) in terms of work to be completed.
#6
Term
Critical Path Method (CPM)
Definition
A schedule network analysis technique used to calculate the theoretical early start/finish and late start/finish dates for all activities. The Critical Path is the longest path through the network diagram and has zero total float.
#7
Term
Total Float vs. Free Float
Definition
Total Float: The amount of time an activity can be delayed without delaying the project completion date.
Free Float: The amount of time an activity can be delayed without delaying the early start date of any successor activity.
#8
Term
Earned Value Management (EVM) Core Metrics
Definition
  • Planned Value (PV): Authorized budget assigned to scheduled work.
  • Earned Value (EV): Measure of work performed expressed in terms of the budget authorized for that work.
  • Actual Cost (AC): Real cost incurred for work performed.
Showing 8 of 21 cards in this deck.