20 cards · Public · Shuffle

PMP Certification - Process Groups & Knowledge Areas

Master the 5 Process Groups, 10 Knowledge Areas, EVM formulas, and Agile concepts to pass the PMP exam on your first try.

Cards in this deck

(20 cards)

Preview terms and definitions before starting your study session.

#1
Term
What are the 5 PMP Process Groups and their core objectives?
Definition
1. Initiating: Define a new project or phase and gain authorization.
2. Planning: Establish scope, refine objectives, and define the course of action.
3. Executing: Complete the work defined in the management plan to satisfy specifications.
4. Monitoring & Controlling: Track, review, and regulate progress to identify required changes.
5. Closing: Formally finalize all activities across process groups to complete the project or phase.
#2
Term
What are the 10 PMBOK Knowledge Areas?
Definition
1. Project Integration Management
2. Project Scope Management
3. Project Schedule Management
4. Project Cost Management
5. Project Quality Management
6. Project Resource Management
7. Project Communications Management
8. Project Risk Management
9. Project Procurement Management
10. Project Stakeholder Management
#3
Term
EVM: Planned Value (PV) vs. Earned Value (EV) vs. Actual Cost (AC)
Definition
  • Planned Value (PV): The authorized budget assigned to scheduled work.
  • Earned Value (EV): The budget assigned to work actually completed.
  • Actual Cost (AC): The total cost incurred for work performed.
#4
Term
EVM Formulas: Cost Variance (CV) & Schedule Variance (SV)
Definition
  • Cost Variance:
  • : Under budget (favorable)
  • : Over budget (unfavorable)
  • Schedule Variance:
  • : Ahead of schedule (favorable)
  • : Behind schedule (unfavorable)
#5
Term
EVM Formulas: Performance Indexes (CPI & SPI)
Definition
  • Cost Performance Index:
  • : Cost efficient (under budget)
  • : Over budget
  • Schedule Performance Index:
  • : Schedule efficient (ahead of schedule)
  • : Behind schedule
#6
Term
EVM Formulas: Estimate at Completion (EAC)
Definition
  • Typical (current CPI expected to continue):
  • Atypical (future work performed at budgeted rate):
  • Bottom-Up:
  • Combining CPI and SPI:
#7
Term
EVM Formulas: Estimate to Complete (ETC) & Variance at Completion (VAC)
Definition
  • Estimate to Complete (ETC): Expected cost to finish remaining work.
  • Variance at Completion (VAC): Expected budget deficit or surplus.
  • : Under or on budget
  • : Over budget
#8
Term
EVM Formula: To-Complete Performance Index (TCPI)
Definition
Calculates the required cost performance needed to meet a specified target ( or ):
  • To meet original budget (BAC):
  • To meet revised estimate (EAC):

(A value indicates harder performance required)
Showing 8 of 20 cards in this deck.