Master the PMP exam with high-yield flashcards covering PMBOK Guide process groups, knowledge areas, Earned Value Management formulas, and core Agile/Hybrid frameworks.

20 accessible of 20 cards

Card Preview

20 accessible of 20 cards

A quick, read-only look at the deck content.

Term

5 Project Management Process Groups

Definition

1. Initiating: Define a new project or phase by obtaining authorization.
2. Planning: Establish scope, refine objectives, and define action plans.
3. Executing: Complete work defined in the management plan.
4. Monitoring & Controlling: Track, review, and regulate progress and performance.
5. Closing: Formally conclude all activities across process groups.

Term

Earned Value Management (EVM): Core Metrics

Definition

  • Planned Value (PV): Authorized budget assigned to scheduled work.
  • Earned Value (EV): Measure of work performed expressed in terms of the budget authorized for that work.
  • Actual Cost (AC): Real cost incurred for work performed.

Term

Schedule Variance (SV) and Cost Variance (CV)

Definition

  • Schedule Variance:
  • : Ahead of schedule
  • : Behind schedule
  • Cost Variance:
  • : Under budget
  • : Over budget

Term

Cost Performance Index (CPI) and Schedule Performance Index (SPI)

Definition

  • CPI:
  • : Cost efficient (under budget)
  • SPI:
  • : Time efficient (ahead of schedule)

Term

Estimate at Completion (EAC) Calculations

Definition

  • If current performance trends continue:
  • If future work will be performed at the planned rate:
  • If original plan is flawed:

Term

Critical Path Method (CPM) & Total Float

Definition

  • Critical Path: The longest path through a network diagram, representing the shortest possible project duration. Float = .
  • Total Float: Amount of time an activity can be delayed without delaying the project completion date ( or ).
  • Free Float: Time an activity can be delayed without delaying the early start of any successor.

Term

Scope Baseline Components

Definition

The scope baseline is an approved, controlled document containing:
1. Project Scope Statement: Project deliverables and acceptance criteria.
2. Work Breakdown Structure (WBS): Hierarchical decomposition of total project scope.
3. WBS Dictionary: Detailed deliverable, activity, and scheduling information for each WBS component.

Term

Work Breakdown Structure (WBS) & Work Packages

Definition

  • WBS: A deliverable-oriented hierarchical decomposition of work.
  • Work Package: The lowest level of a WBS where cost and duration can be estimated and managed.
  • 100% Rule: WBS must include 100% of the work defined by project scope and no extra work.